March 30, 2006

TriMet to perform routine maintenance

Westside work on transformers to begin next week

Starting Monday, April 3rd, TriMet will perform annual maintenance on MAX transformers. Train stations and platforms will be without power from approximately 9 a.m. to 1 p.m. This outage will affect power to the ticket vending machines and TransitTracker. The outage will not affect the signal system.

Maintenance schedule:

Monday, April 3rd - Washington St. in Hillsboro
Tuesday, April 4th - PGE Park
Wednesday, April 5th - Beaverton Transit Center
Thursday, April 6th - Fair Complex/Hillsboro Airport

TriMet plans to complete maintenance at other Westside stations over the next few weeks.